Before anyone can argue about whether the data-center load stacking up in the interconnection record is real, there is a plainer question that has to be answered first: can you see it at all? This is the record, operator by operator, with the documents we read and the date we read them.
As of the documents dated in each entry below — this is a survey, and it describes the record as we read it, not a live feed.
11, IA Completed, and in the file read from NYISO on 3 October 2026, whose rows carry updates through 30 September 2026, nobody sits there: four
requests stop a step short, while eight are already under construction or in service and so
plainly cleared that stage. The IA Tender Date column is empty on all 74 rows,
theirs included. The record follows a large load all the way to commercial operation without
ever showing when it signed. The table below shows where each of the others stands.Those two findings belong together, and they are the reason this page exists. What is missing from the public record is narrower than a blanket absence, and more specific than a general call for transparency. It is one field, in a file that in at least one market already exists.
| Operator | What is published per request | In one line |
|---|---|---|
| NYISO | Per-request list, with status | A dedicated load tab in the public queue workbook: 74 requests with status, zone, and a published end-use class that names AI data centres. |
| MISO | Per-request list, different unit | A per-request table exists and carries a status field — but the row is a transmission project, not a load request. |
| ERCOT outside full FERC jurisdiction | Aggregate only, by rule | A monthly public report is mandated — and the same protocol requires aggregation and forbids per-request disclosure. |
| CAISO | No per-request list | No public large-load queue — and CAISO has recommended in writing that the utilities adopt one. |
| ISO-NE | No per-request list | Tracks per-project maturity internally, publishes a two-project forecast table with no status column. |
| SPP | Not established | Not established. The 2025 revision does require an OASIS listing, but the requests it names are for generating facilities, not for the load. |
| PJM | Not established | Not established. Its public queue is a generation queue with no load category — but that is not where large load would appear. |
Each entry states what is published, whether a status field exists, what that field actually measures, and how the document reached us.
The public queue workbook NYISO-Interconnection-Queue carries a dedicated Load Projects tab alongside generation. In the file read from NYISO on 3 October 2026, whose rows carry updates through 30 September 2026, it holds 74 load interconnection requests, each with a queue number, developer and project name, submission date, peak MW, county, NYISO zone, point of interconnection, utility and a status value; withdrawn requests are kept and counted separately. A companion Load Project Tracking tab publishes the same population summarised three ways — by status, by end-use and by submission year — each broken out across the NYISO zones.
Status field. Yes — Project Status #, and the file carries its own key. The early rungs track the studies, from a scoping meeting through feasibility, reliability-impact and facilities studies, with withdrawal available throughout. The rungs that matter for this survey are the later ones, which we quote rather than paraphrase: 10 Accepted Cost Allocation/IA in Progress, 11 IA Completed, 12 Under Construction, and then 13, 14 and 15 for service, in test, commercial and partial. So the ladder names the executed interconnection agreement explicitly, and carries four further rungs beyond it.
DAT Data Center (general) · DAT-AI AI Datacenter · DAT-CM Cryptocurrency mining · M-CH Microchip fabrication · M-CG Consumable Goods · M-IN Industrial Goods · RD Research and Development · HP Hydrogen Production · O Other. In this file the three data-centre classes account for 11,887.9 MW of the 13,611.9 MW classified — 87% — of which 5,266 MW is declared AI datacenter, broken out by zone. We report that class, and the four things it cannot tell you, at index.loadstar.energy/ai-load.10, agreement in progress, and none sits at 11. Eight sit further along still — four under construction, four in commercial service — so those eight plainly cleared the agreement stage. And yet the IA Tender Date column is empty on all 74 rows, theirs included. The file therefore follows a large load from first study to commercial operation without ever recording when the agreement happened. We are describing the record, not the world: those agreements plainly exist. They are simply not in the file.S, reported 51 rows and 12,670.1 MW, and said no row sat at 10 or 11. Reading the live file corrected all four — and turned up the end-use classification, which we had missed entirely. The custody note below explains how we came to be working from an archived copy in the first place.MISO does not operate a load interconnection queue; large-load requests go to the transmission owner. What MISO publishes is a per-row table of Expedited Project Review cycles — transmission projects whose dominant driver is large load. The columns are EPR Cycle · Project ID · Project Description · MISO Region · Transmission Owner · Load Value (MW) · Current Status.
Status field. Yes, Current Status — and it does not answer the question. Its values (Under Study, Approved) track the progress of the transmission project's study, not the commercial maturity of the load behind it. An outside reader cannot use it to separate load with an executed agreement from a request without one.
ERAS (Expedited Resource Addition Study), EPR (Expedited Project Review), ZGIA (Zero-Injection Interconnection Agreement), and a further study process it describes as under development. What the page does not contain is a list: the words status, queue and MW appear zero times on it. We report this because it is the operator's own page for the subject of this survey, and it is the strongest available basis for the verdict on this row.+.A monthly public report on large-load interconnection requests, required by §3.2.7 of the ERCOT Nodal Protocols (created through NPRR1267). A public report on large load is therefore mandated here by rule, and that is what makes the case instructive: it shows what a mandate of this shape does, and does not, produce.
Status field. Not in this report. The dimensions the §3.2.7 monthly report is required to carry do not include a status or commitment field. Taxonomies ERCOT publishes beyond those dimensions are reporting practice rather than a protocol requirement — and what the Batch Study process publishes separately, we have not established.
Nothing per request. CAISO's PublicQueueReport.xlsx has three tabs, for active, completed and withdrawn requests, and all three are generation. Our reading of the file finds the word load zero times in the entire workbook.
Status field. Not applicable — there is no large-load list to carry one.
The only per-project large-load data published is a table of two projects included in the forecast — one 200 MW data center in the NEMA zone and one 85 MW electrification project in Connecticut — with the columns Load Zone · Project Type · Reported Nameplate · Timeline. There is no status column and no request identifier. It is a list of what has been folded into the forecast, not a queue.
Status field. No. And the omission is visible from the outside, because ISO-NE publishes the maturity ladder it uses internally — a stepped completion probability running from a signed study agreement, through a completed interconnection study and a construction agreement, to commercial operation. The ladder is public; which step a given project stands on is not.
ISO Action: Approved, Notification, Approved Withdrawn, Approved with conditions, Not approved) and it is not a large-load list. We parsed 5,905 rows and found zero hits for data center, hyperscale, crypto or large load. It should not be described as one.The revision requires an OASIS listing, and the unit it names is not the load. SPP's board approved Revision Request 696, Integrate & Operate High Impact Large Loads, on 4 September 2025. We read the revision in full. It provides, verbatim, that “HILLGA Requests shall be listed on the Transmission Provider’s OASIS along with all other Interconnection Requests”, and it creates a named agreement instrument for large load, the HILLGIA, executed copies of which are filed at the Commission.
Read against the revision's own definitions, that clause does not reach the load. The same document defines a HILLGA Request as an Interconnection Request made under the High Impact Large Load Generation Assessment procedures to interconnect a new Generating Facility, or to increase the capacity of an Existing Generating Facility. What section 3.5.1 posts to OASIS is therefore the on-site generation that supports a large load, not the large-load request itself, which the revision routes through a separate delivery-point study. We corrected this on 21 August 2026: an earlier version of this row read the clause as covering large-load requests, which the definition does not support.
Two things stop us calling it a finding. First, board approval is not an effective tariff: SPP's own comment record contains an intervenor objecting that SPP “will move forward with implementing RR 696 prior to FERC approval”, and we did not establish whether the Commission has accepted it. Second, OASIS refused our connection, so we could not look at what is actually listed there or whether it is reachable without an account.
Under the older tariff path, large-load requests are submitted by email, to a load studies mailbox, under Attachment AQ or AX, and study reports go to the customer — no queue file, no request identifier, no status ladder. That is not the whole picture, and we had it as the whole picture. SPP's board approved a dedicated High Impact Large Load (HILL) framework on 4 September 2025, through Revision Request 696, which folds transmission service, generation and load interconnection and reliability studies into one process with a 90-day study-and-approval clock. SPP's own announcement describes it as accelerating load interconnection through “integrated design, study, registration and operations” and names transparency among the benefits for developers.
Status field. Not established. The older tariff path produces no request record to attach a status to. The 2025 revision would put large-load requests on OASIS beside generation requests, which carry status — but we could not reach OASIS to see what is shown, and we did not establish that the revision is in effect.
CHILL, a conditional service offering faster access in exchange for possible curtailment, and HILLGA, an assessment that studies a large load and its supporting on-site generation in parallel. The page states a target of reaching interconnection agreements within 90 days. It also carries a running series of Large Load Processes Q&A meetings with published materials and transcripts, the most recent listed for 6 August 2026 and a further session scheduled for 17 September 2026. What the page does not carry is a list: the words status, queue and MW appear zero times on it. This does not resolve the row, because the obligation described above runs to OASIS and OASIS is what we cannot reachPJM publishes a per-request queue — the Cycle Service Request Status table, with the columns Project ID · Name · State · Status · TO · MFO · MW Energy · MW Capacity · MW In Service · Fuel. Read live on 20 August 2026, its own Fuel filter offers sixteen values and every one of them is a generation fuel: biomass, coal, fuel cell, hybrid, hydro, methane, natural gas, not specified, nuclear, nuclear fusion, offshore wind, oil, other, solar, storage, wind. There is no load category, and the page returns no hits for large load, data center, crypto or hyperscale. That does not make PJM a “no”. This is the generation interconnection queue; a large load would not travel through it in the first place, so its silence is expected and answers a question we did not ask. Where a PJM large-load request would be recorded, and whether that record is public, is what we have not established.
Status field. Not established.
Fuel filter are all generation fuels, and there is no load row type. We record the claim and its refutation rather than quietly dropping it.On 18 June 2026 the Commission issued show-cause orders on large-load transparency across the RTO and ISO regions. Since they are the obvious place to ask whether the gap described above is already being closed, we read the orders themselves rather than summaries of them: the PJM order (Docket EL26-67-000, 195 FERC ¶ 61,211) and the ISO-NE order (Docket EL26-72-000, 195 FERC ¶ 61,215) in full, each obtained from the operator it is addressed to. A third, addressed to CAISO, is Docket EL26-71-000. We take no position on what the Commission should do; what follows is what the text says.
Corrected 21 August 2026. An earlier version of this page said six proceedings were opened, Dockets EL26-67 through EL26-72. We could not establish that count from the orders themselves, and the paragraph numbers around them include orders on other subjects, so we now state only what the documents show.
This is a survey of public documents, and it will be wrong before it is old. If you operate one of these markets, or you have read a file we have not, we would much rather hear it than leave it uncorrected — tell us, and we will date the correction in the open.