Every quarter, Georgia Power tells the Georgia Public Service Commission how much large-load demand is in its pipeline, how much customers have committed to, and how much has broken ground. We read each report twice, independently, archive it with a SHA-256 fingerprint, and show the figures as the utility wrote them, with the page they come from.
| Quarter | Total pipeline | Large-load pipeline | Committed | Broken ground | Near term: broken ground / committed |
|---|---|---|---|---|---|
| Q1 2026 filed 2026-05-15 · document · p.5-7 | 76,200 | 73,100 | 12,400 | ~8,500 | 6,800 / 7,800 |
| The report notes commitments of 3,200 MW added in April 2026 that are not included in these values. Table 1 gives broken ground as 8,493 MW. | |||||
| Q4 2025 filed 2026-02-11 · document · p.5-7 | 69,100 | 65,900 | 11,800 | 7,970 | 6,200 / 6,900 |
| From this quarter, commitments count Contracts for Electric Service plus Requests for Electric Service. The cover letter is dated February 11, 2025; the filing date at the PSC is February 11, 2026. | |||||
| Q3 2025 filed 2025-11-21 · document · p.5-8 | 53,500 | 50,900 | 11,000 | 7,313 | 6,175 / 7,800 |
| The same report also states commitments as 10,999 MW (p.8). From this quarter, 'committed' means customers that have, at a minimum, executed a Request for Electric Service. | |||||
| Q2 2025 filed 2025-08-15 · document · p.5-7 | 59,000 | 56,800 | 8,799 | 3,721 | 3,265 / 6,261 |
| The report's Table 2 rounds broken ground to 4,000 MW; Table 1 and the next report's text give 3,721 MW. | |||||
| Q1 2025 filed 2025-05-22 · document · p.5-7 | 54,600 | 52,100 | 8,274 | 3,721 | 3,265 / 5,646 |
| Q4 2024 filed 2025-02-21 · document · p.5-7 | 46,100 | 44,200 | 8,274 | 3,721 | 2,951 / 4,885 |
| Q3 2024 filed 2024-11-18 · document · p.5-7 | 36,500 | 34,600 | 8,046 | 3,721 | 3,000 / 4,900 |
| Q2 2024 filed 2024-08-16 · document · p.5-7 | 24,300 | 22,800 | 7,252 | 3,776 | 2,900 / 4,600 |
| Q1 2024 filed 2024-05-15 · document · p.5-6 | ~21,000 | ~19,600 | 6,187 | 3,478 | 2,300 / 4,100 |
| This report also counts projects that have broken ground or are pending construction together (6,121 MW); that is a different measure and is not shown as broken ground. | |||||
Pipelines run through the mid-2030s. “Near term” is the winter of 2028/2029, as the reports use it. “~” marks a figure the report itself gives as approximate. Where a report states one figure in two ways, the note under that quarter says so.