FREE TO CITE

THE LOADSTAR NUMBER

the signed share of the seven ISO/RTO generation interconnection queues

New power plants in the U.S. wait in line to connect to the grid. LOADSTAR reads the queue files of the seven U.S. ISOs and RTOs every day and publishes one number: how much of the capacity in line shows an executed interconnection agreement in the operator’s file. Why it matters. New electricity demand, AI data centers included, needs new supply. This is the generation and storage capacity waiting to connect, as requested, not what will be built.

READING25.7% signed, a floor

Of the 1,177.7 GW requested in the seven U.S. ISO/RTO generation interconnection queues (active requests of 50 MW and up), 302.1 GW, about 25.7%, shows an executed interconnection agreement in the operators’ own queue files. We treat it as a floor, not a forecast: anything the files do not show counts as unverified. Two caveats: in NYISO the status is read from the project stage, and MISO’s active list shows almost none (0.1%); without MISO the share is 33.3%.

‘Signed’ = the operator’s file shows an executed interconnection agreement or, in NYISO and PJM, a project stage we read as one (rule per queue at /verify). 6 of 7 queues yield a meaningful signed share (CAISO, ISO-NE, SPP, ERCOT, NYISO and PJM); any queue not listed sits in the denominator with little or nothing in the numerator. We treat 25.7% as a floor, not a forecast. Unverified ≠ phantom. Descriptive of today. The full caveat is one click below. Full criteria.

Free to cite · CC BY 4.0 · live JSON at /api/numbers
How much of the queue shows a signed agreement?
~26% — a floor, not a forecast
Of 1,177.7 GW requested across the 7 U.S. ISO/RTO generation queues (active requests of 50 MW and up), 302.1 GW shows an executed interconnection agreement in each queue’s own published status data — and the share varies widely where queues publish it: CAISO 81% · ISO-NE 67% · SPP 48% · ERCOT 29% · NYISO 25% · PJM 17%. No signed agreement shown means only that the file shows none.
Is this the data-center queue?
No — it is the generation queue
The power plants and storage seeking to connect and serve future load growth, of which AI data centers are one driver. It is not a queue of data-center requests — most ISOs do not publish those. The demand side, where one operator does disclose it, is at /ai-load.
Who verifies intent?
No one publishes it
No queue publishes intent — an executed agreement is the closest public proxy, and in 1 of the 7 queues even that can’t be turned into a comparable share by our reading (MISO is read but structurally near-zero). That is why this index exists: a public, dated, recomputable reading of how much of the requested capacity shows a signed agreement.
The queue’s total requested capacity now exceeds the highest hourly demand the United States has ever recorded.
1,177.7 GW of requests on file vs the all-time U.S. hourly demand record of 759.2 GW — requested capacity, not coincident demand (EIA, July 29, 2025).

CITE IT

“Of the 1,177.7 GW requested in the seven U.S. ISO/RTO generation interconnection queues (active requests of 50 MW and up), 302.1 GW, about 25.7%, shows an executed interconnection agreement in the operators’ own queue files. We treat it as a floor, not a forecast: anything the files do not show counts as unverified. Two caveats: in NYISO the status is read from the project stage, and MISO’s active list shows almost none (0.1%); without MISO the share is 33.3%.” — LOADSTAR
Live JSON: index.loadstar.energy/api/numbers · Method: /methodology · Press kit: /press